Updated by SLA Yes. You may liaise directly with the relevant competent authorities for a power load that is higher than the prescribed maximum load as advised by SP Power Grid Ltd. The provision of a direct service connection is dependent on the available network capacity in the vicinity. If there is insufficient capacity, you are required to provide a substation for the connection. Contact us
May we apply for a power load that is higher than the approved maximum load?