May we apply for a power load that is higher than the approved maximum load?


sla-logo
Updated by SLA
Yes.  You may liaise directly with the relevant competent authorities for a power load that is higher than the prescribed maximum load as advised by SP Power Grid Ltd.  The provision of a direct service connection is dependent on the available network capacity in the vicinity.  If there is insufficient capacity, you are required to provide a substation for the connection.